W4_Muslem_Three-Point (PERT) Cost Estimation for Utilizing Extranet Service
Problem Statement:
Extranet is an important element
in OPWP procurement for the purpose of sharing tender documents and information
with suppliers. Currently, OPWP does not utilize extranet, but relies on
contracted advisors to provide this service. In some cases, advisors charge
high cost for it. This report will provide a cost estimate for OPWP if it
decided to procure this service separately.
Feasible Tendering Options:
There are
three tendering options; single tender, limited tenders and open tenders [1]. The
cost for the last two options will be estimated under this report for the
reasons explained in the next section.
Outcomes of each option:
My previous
blog has assessed the three options, and the following are found [2];
·
Single tender mode cannot be adopted due to OPWP's procurement obligations.
·
Limited tenders’ mode could lead to less
competitive bids due to reduced competition, but shorter lead time.
·
Open tenders’ mode could be time and effort
consuming due to uncertainty in number of tenders submitted. However, it could
lead to more competitive prices.
Selection of Criterion;
OPWP has to
adhere to its obligation for economic purchase. Therefore, it is essential to choose
the option that would lead to obtain low priced tenders.
Analysis and Cost estimates of Options:
For the procurement of the service
at hand, it is assumed that most tenderers would be known locally. This is because
that the tender advertisement will be placed locally. Therefore, very minor difference
in procurement cost using both options is expected.
The extranet cost can be divided
into two sub-costs; portal development cost and hosting cost. As per our IT
Department, the cost for hosting 5GB of data is approximately 1,000 per
year. Our largest project has required
2.6 GB storage for data. The maximum number of large scale projects procured in
one year in PD Department is 6 projects. Therefore, 15GB is required, meaning
the annual cost of hosting is approximately OMR 3,000.
The following table shows cost of
the basic portal development by a number of supplier.
Suppliers
|
Cost (OMR)
|
Supplier A
|
4,000
|
Supplier B
|
1,925
|
Supplier C
|
5,000
|
Supplier D
|
2,175
|
Supplier E
|
3,000
|
Supplier F
|
2,400
|
Average
|
3,080
|
Three-point (PERT) estimation is
most common estimation technique [3]. The PERT estimate formula is Ce = (Co+4Cm+Cp)/6,
where;
Most
likely Cost (Cm): Average cost of OMR 3,080 is considered in
this case for Cm.
Pessimistic
Cost (Cp): The worst case is OMR 5,000.
Optimistic
Cost (Co): The best case is OMR 1,925.
Therefore, the expected portal development
cost is approximately OMR 3,200 for both options.
Selection of Preferred Option:
Although both options are rated
equally under this assessment in term of service cost, open tendering option is
preferred in the analysis conducted on the previous blog. Therefore, open
tendering mode is the best overall.
Recommendations and Performance Monitoring:
The following table shows cost
estimates for the procurement of extranet service in OMR. It is recommended to
consider 10% contingency above estimated cost for budget planning.
Items
|
Estimated
Cost (OMR)
|
Portal
Development
|
3,200
|
Annual
Hosting Cost
|
3,000
|
Contingency
(10%)
|
620
|
Total
|
6,820*
|
*OMR 3,000 to be paid
on an annual basis.
The annual hosting cost can be
adjusted depending on the required size as per undergoing projects in each
year.
References:
[1] Central Vigilance Commission (ND), Tendering stage, PDF.
Retrieved from; http://cvc.nic.in/3%20Tender%20Stage.pdf
[19 November 2017].
[2] Muslem.
A (2017). Assessing Tendering Options for Extranet Service Using Decision
Matrix Analysis. Retrieved from; http://pmpopwp.blogspot.com/2017/12/w31muslemtendering-options-for-extranet.html
[05 December 2017].
[3] PM Study Circle
(ND), 4 Tools to Estimate Costs in the Project Management. Retrieved from; https://pmstudycircle.com/2012/06/4-tools-to-estimate-costs-in-the-project-management/
[20 November 2017].
Great case study but how or why did you arbitrarily decide to allow a 10% contingency? What p level does a 10% contingency does that provide for you?
ReplyDeleteAlso your average (P50) was 3,080 how was it you calculated 3,200?
I am going to REJECT this posting and ask you to do it over again but this time show us what P level your MANAGEMENT as adopted as a STANDARD and then redo your calculations using PERT and the Z tables as you were taught in class. What you have done here appears to be exactly what you should NOT be doing.....
BR,
Dr. PDG, Jakarta
Dr. PDG, Jakarta