W6_Hilal_Forensic Schedule Analysis (Part Three)
Problem Recognition
Each month we receive schedule updates from the project
companies as part of their monthly reporting and it is important to conduct a
delay analysis to discover any current delays or emerging delays. In weeks 4
& 5 blogs, the discussions were over observational methods and modeled
methods respectively to be used as schedule analysis method. Now, I need to
compare both methods to see the possibility of using both methods to come up
with robust analysis of the reported schedule.
Feasible alternative
The Guild of Project
Controls Compendium and Reference suggests an observational and modeled
approaches to forensic schedule analysis. These approaches consist of:
a.
Observational Static Logic
b.
Observational Dynamic Logic
c.
Modeled Additive Model
d.
Modeled Subtractive Model
Outcomes of alternative
-
Static Logic: it compares
as-planned vs as-built schedules to provide an overall analysis. It can be done
in one segment or multiple segments to provide more accurate analysis. Although
it is simple and easy to understand, this method is not suitable for
complicated project with multiple critical paths and concurrent delays.
-
Dynamic Logic: it compares
schedule updates to as-built schedule where it accounts for changing scenarios.
It requires that the reported progress is accurate, therefore, it consumes a
lot of time, thus, a lot of money.
-
Additive Model: it involves
the adding of schedule elements (i.e. delays) to the as-planned schedule and
comparing it with as-built schedule. “Impacted As-planned”.
-
Subtractive Model: it
involves the subtracting of schedule elements (delays) from the As-Built
schedule and comparing with the As-planned schedule. “Collapsed As-built”.
Acceptance Criteria
Due to the importance of
delay analysis, contractual requirements, and available resources the
acceptance criteria is as follow:
1-
Accounts for critical path
shifts
2-
Susceptible to manipulation
3-
Required records
a.
Baseline Schedule
b.
Schedule updates
c.
As- Built Schedules
4-
Purpose of analysis
a.
Compensable vs
Non-Compensable Delays
b.
Constructive acceleration
5-
Required resources
a.
Time
b.
Money
c.
Expertise
Acceptance Criteria vs Feasible Alternative
Acceptance Requirements
|
Importance Scale
|
Static Logic
|
Dynamic Logic
|
Additive
|
Subtractive
|
|||||
A
|
B
|
B*A
|
C
|
C*A
|
D
|
D*A
|
E
|
E*A
|
||
Critical Path Shift
|
11
|
1
|
11
|
3
|
33
|
3
|
33
|
3
|
33
|
|
Manipulation
|
1
|
3
|
3
|
3
|
3
|
3
|
3
|
3
|
3
|
|
Baseline Schedule
|
7
|
2
|
14
|
1
|
7
|
3
|
21
|
1
|
7
|
|
Schedule Updates
|
6
|
1
|
6
|
1
|
6
|
3
|
18
|
3
|
18
|
|
As- Built Records
|
5
|
2
|
10
|
3
|
15
|
2
|
10
|
3
|
15
|
|
Non-Compensable Time
Extension
|
9
|
3
|
27
|
3
|
27
|
3
|
27
|
3
|
27
|
|
Compensable Delay
|
8
|
3
|
24
|
3
|
24
|
1
|
8
|
3
|
24
|
|
Constructive Acceleration
|
10
|
1
|
10
|
3
|
30
|
3
|
30
|
1
|
10
|
|
Time
|
4
|
3
|
12
|
2
|
8
|
1
|
4
|
1
|
4
|
|
Money
|
2
|
3
|
6
|
1
|
2
|
1
|
2
|
1
|
2
|
|
Expertise
|
3
|
3
|
9
|
1
|
3
|
1
|
3
|
1
|
3
|
|
|
|
Total
|
132
|
Total
|
158
|
Total
|
159
|
Total
|
146
|
Table 1: Analysis of
Feasible Alternatives
Table 1 compares the
acceptance criteria against the feasible alternatives. Column A represents the
importance scale where 11 is highly important. Columns B, C, D & E show how
the alternatives are meeting the requirements where 3 means meeting the
requirements.
Preferred Alternative
Although Table 1 suggests
that either Observational Dynamic model or Modeled Additive Model can be used.
However, it is possible to combine both models to be used to assess the schedule
by comparing the results from both analyses. We will be able to assess the
schedule not only by observing the behavior of the network from update to
update and measuring schedule variances based on unaltered, existing logic
models but also by insertion or addition of activities representing delays or
changes into a network analysis model representing a plan to determine the
impact of those inserted activities to the network.
Tracking/ reporting plan
These methods are to be
used to analyse delays in the reported schedules. Then, we can compare the
findings of both methods and then to be used to develop worst case scenarios.
The effectiveness of the methods as well as the resource requirements need to
be reported to the management in order to use this method in future projects.
Reference
Avalon, A. (2016). Choosing the Most Appropriate Schedule Analysis
Method. Retrieved from
http://www.long-intl.com/articles/Long_Intl_Choosing_the_Most_Appropriate_Schedule_Analysis_Method.pdf
Lifschitz,J.
Evans, M & Alexis M. (2009). A Critical Review of the AACEI Recommended
Practice for Forensic Schedule Analysis. CONTRACT FORMS AND CONTRACT
DRAFTING/PROJECT DELIVERY. Retrieved from http://www.slslaw.com/sites/default/files/Construction%20Lawyers%20Reprint%2010-09%20(00076022).PDF
PP Admin. (2015). Multi- Attributes Decision. Guild
of Project Controls Compendium and References. Retrieved from http://www.planningplanet.com/guild/gpccar/managing-change-the-owners-perspective
Yerramreddy,
V. (2014). Schedule Quality- Delay Analysis Perspective. Retrieved from https://repository.tudelft.nl/islandora/object/uuid:fd3c938d-2207-41c6.../download
AWESOME conclusion, Hilal!!! Really nice work on your review and analysis of the different methods.
ReplyDeleteIF you want to continue on this topic, then I HIGHLY recommend that you read over the work of Jim Zack on "Games Contractors Play with Schedules"....
https://www.constructionjunkie.com/blog/2015/5/31/19-scheduling-games-contractors-play-and-how-to-stop-them
https://cmaanet.org/files/publications/Articles/Construction%20Scheduling%20Games%20-%20Revisited.pdf
https://www.navigant.com/-/media/www/site/insights/construction/2015/earlycompletionschedules_ifh15.pdf
https://www.linkedin.com/pulse/19-scheduling-games-contractors-play-how-stop-them-leo-reis/
This was one of the big inputs to the GAO's "Best Practices in Scheduling"........
Keep up the good work and looking forward to a really great paper from this research...
BR,
Dr. PDG, Jakarta