W6_Afra_Cost and Time Trade-Off part 3
1. Problem
Recognition
There is a
relationship between project’s completion time and its cost. By understanding
the time-cost relationship, one is better able to predict the impact of a
schedule change on project cost.
The previous
two blogs discussed the contractor's curve and the owner's overhead and lost
opportunities cost curve as shown in figure 1 below which provides a great
illustration that is based on the US Department of Transportation.
This blog is
the final blog in a series of three blogs about time and cost trade-off which
will answer the question of: How fair is a Bonus/Penalty system and when should
it be developed? To answer such question, this blog will develop the final
curve of the Total Cumulative cost and finalize the chart of the conceptual
project and determine the ‘Bonus/Incentive’ or ‘Penalty/Disincentive’ against
the criteria selection.
Figure 1 – Relationship between project cost
and duration
2. Feasible alternatives
There are two alternatives:
1.
Bonus
(Incentive)
2.
Penalty
(Disincentive)
And these depend on the Contractor’s
performance and what they are doing in order to achieve targets.
As mentioned above, the three blogs represent
three different curves which are:
1.
Total
Contractor’s Costs
2.
Cumulative
Owners Project Overhead and Lost Opportunity Cost
3.
Total
Cumulative Project Costs
3. Development of the
outcome of Alternative
OPWP
is the purchaser of power and water in the Sultanate and is responsible for
securing the demand for electricity and water for every single day for the
public. and to do so, the company shall contract with Engineering, Procurement,
and Construction (EPC) to build required power and water projects.
The
overall cost estimation for power generation includes the auxiliary costs which could be the land cost, gas purchase,
and the portion of EPC for design, procure and construct and all the
associated owner’s costs for the Project Management Team (PMT) and office.
The Total Project Cost curve is equal to
Contractor’s Cost curve plus Owners project overhead and lost opportunity cost
curve, along with the conceptual project. Figure 2 below shows the total cumulative
cost from month 30 to month 50.
Figure 2 – Total Cumulative Project Costs
Curve
The curve above shows the cumulative
sum of the previous two curves. Moreover, it shows the owner’s target duration
and owner’s optimum duration, in term of contractor’s, the duration and cost
are in the agreed contract which assumed to be 1.5B and 43 months. In addition,
The Owner’s optimum costs are where the cost curve is the lowest and at what
point it occurs, in the model, this is 4.4B and 38-months.
The figure below shows the Bonus/Penalty
zones by putting all three curves in one. The base of duration overrun is 46.
Figure 3 –
Schedule vs Time Optimization Model
To conclude, the incentive zone is the trending of
contractor's optimum duration and owner's optimum duration in the Y-axis. On
the other hand, the disincentive zone is the difference in the Contractor’s
optimum cost vs the higher data-point of the Duration overrun (the lost
opportunity costs).
4.
Selection Criteria
By analyzing figure 3:
Incentive
|
disincentive
|
The upper value = 4B and the lower value = 3.2B, therefore the
incentive is 0.8B (4-3.2) which needs to be broken down into a daily basis
(0.8/(4*30) = 6.6M/day).
|
On month-46 intersection with the ‘Owner’s overhead and
opportunity’ line equal to 2.9B, and the Contractors optimum cost which is
the bid value of $2.4. the disincentive is 0.5B which also needs to be converted into a daily rate (5.5M/day for
any delivery after the end of the 43 months).
|
Table 1 –
Incentive vs disincentive
The incentive amount
mainly used by contractors to cover the expenses/inefficiencies associated with
acceleration to complete the project faster. The benefit for contractors is to reduce
their overheads by shortening of the project duration.
5.
Analysis and
comparison of the Alternative
As mentioned above,
this blog supposes the answer the question of: How fair is a Bonus/Penalty
system and when should it be developed?
Finishing the project
earlier, sometimes, is significant for the owner. Moreover, contractors always
keep in their mind that the project owner may ask them to complete the project
earlier by providing a bonus, which is good!
But also keeping in mind failure to achieve the deadline could result in
penalties from the Owner, and as mentioned above, the $0.8B incentive value is
to purely cover the expenses and inefficiencies associated with the
acceleration, likewise, the $0.8B penalty is to cover the lost opportunity
costs.
To include such
details in the contract, the owner the associated personal should be very
careful, likewise the contractor.
The best time to
include Bonus/Penalty at time of developing the contract since it needs a full
agreement between all parties prior to implementation.
6.
Selection of the
preferred Alternative
It's not a situation
to choose the best alternative between Bonus and Penalty. However, the bonus is
a very attractive alternative for the contractors which will let them do their
best to get it, from the other side, they will start thinking about the penalty
from the first day of the project since they will pay a daily amount of money for
failure to meet the optimum duration.
7.
Performance Monitoring
and the Post Evaluation of result
No one curve fits all
approaches or projects. The projects are varying in their nature, size, urgency
and have a different way of acceleration, which will always generate different
curves with different values. Hence, the concept remains the same.
In future research, it
is recommended that, various degrees of confidence levels for example, and
various values for the coefficient of variation.
References:
1. Mallela, J., & Sadasivam, S. (2011). Figure 15 –Work zone
road user costs: Concepts and applications : final report. U.S. Department of
Transportation, Federal Highway Administration Office of Operations (HOP).
2.
Guild of Project
Controls. (n.d.). 08.7.3 – Cost vs Time Trade Offs (Optimization) – Guild of
project controls compendium and reference (CaR) | Project controls – planning,
scheduling, cost management and forensic analysis (Planning Planet). Retrieved
September 5, 2017 from
http://www.planningplanet.com/guild/gpccar/validate-the-time-and-cost-trade-offs
3.
W20_SJP_Cost
& Time Trade-off Part 3 - Achieving Guild of Project Controls / AACE
Certification BLOG. (2017). Achieving Guild of Project Controls / AACE
Certification BLOG. Retrieved 10 December 2017, from https://js-pag-cert-2017.com/w20_sjp_cost-time-trade-off-part-3/
4.
W5_Afra_Cost
and Time Trade-Off part 2. (2017). Pmpopwp.blogspot.com. Retrieved 11 December
2017, from http://pmpopwp.blogspot.com/2017/12/w5afracost-and-time-trade-off-part-2.html
5.
W4_Afra_Cost
and Time Trade-Off Part 1. (2017). Pmpopwp.blogspot.com. Retrieved 11 December
2017, from http://pmpopwp.blogspot.com/2017/11/w4afracost-and-time-trade-off-part-1.html
WOW!!!!! AWESOME!!!!! This is such IMPORTANT information that so few owner companies fully realize how to calculate much less use effectively as both a "carrot" and "stick" approach to getting their projects finished faster.
ReplyDeleteI really wish you the very best of luck in "selling" this concept to your management even if they only do it on a pilot project basis to get started.
Keep up the great work, Affra!!!
BR,
Dr. PDG, Jakarta