W12_Afra_Incentive Contracting Approaches
1. Problem
Recognition
Incentive
contracts are entered when there is some uncertainty in the cost of work,
particularly when a product is being built to unique specifications. These
contracts specify the amount of profit or fee payable under the contract for a
contractor's performance. Incentive contracts establish a target price, target
profit and a maximum cost. This is common in contracts involving test programs
or modern technology or processes. Incentive contracts are designed to motivate
contractor efforts that might not otherwise be emphasized and discourage
contractor inefficiency and waste.
In my previous
blog (w10) I developed an analysis to indicate the best contract to be used be
the company, and as a conclusion, the Incentive contracts was the best among
others, in this blog I choose to go deeper and see which of the incentive
contracting approaches might be appropriate, as a suggestion from PDG.
2.
Feasible alternatives
In this blog,
I’ll compare between five common approaches of incentive
contracts:
1.
Cost Plus Incentive
2.
Fixed Price Incentive
3.
Lane Rental Approach
4.
Incentive/Disincentive
5.
A+B or Cost-plus-Time
Figure
1: Approaches of
incentive contracts
3. Development of the
outcome of Alternative
In this
section, will have a comparison between the five approaches of incentive contracts
in their advantage and disadvantage. Table 1 shows the comparison.
Type
|
Advantage
|
Disadvantage
|
Cost
Plus Incentive
|
· Having
good documentation of the costs will assure that the organization is not
paying for something that was not completed.
· Encourage
performance in areas critical to the project.
· Motivate
contractors to save or reduce project costs.
· Keep
the cost of production as low as possible.
|
· Organization
will take the risk of increasing the project cost when the costs of the work
are not well known.
· Reduces
the amount of money the bidders place in the bid to account for the risk
associated with potential increases in costs.
|
Fixed
Price Incentive
|
·
Offers a predictable cost.
· Protect
against escalating cost.
· Provide
a stated price.
|
· The
costs associated with project change if a change occurs on the project that
requires a change order from the contractor.
·
May contain an economic price
adjustment tied to an appropriate index.
|
Lane
Rental Approach
|
· Minimize
the impacts of a project.
· Creates
a monetary incentive for the contractor to be innovative and minimize the
duration of project closures.
· Encourage
contract efficiency and productivity.
· contractors
will take safety risks to reduce lane-rental charges.
|
· Not
necessarily reduces project completion time.
· Requires
additional agency resources.
· Makes
contract change negotiations difficult.
· Requires
additional documentation and coordination.
|
Incentive/Disincentive
|
·
Provide encouragement for contractors
to complete projects by giving them incentives to finish ahead of the
required schedule.
· Financial
disincentives would be collected from the contractor to make up for the loss
of user costs if a project completion was delayed.
|
· Too
much focus on financial reward and not enough focus on other aspects of work.
· Additional funding may be required.
· Contract changes can lead to disputes
regarding the incentive payments.
·
Incentive amount or disincentive rate
may not be enough to motivate the contractor to accelerate project.
|
Cost
plus Time
|
· Reduces
project congestion and delays.
· Encourages
bidders to develop more detailed and well thought out plans.
· Encourages
contractors to develop innovative means of reducing overall project time at
the lowest cost.
· Encourages contractors to schedule project
operations in a manner that maximizes the efficiencies of resources and
equipment.
|
·
Contractor must take time to develop
a reliable schedule.
·
Contract changes are magnified, which
means when there are too many changes, the advantages of cost + time are
nullified.
·
More resources might be needed for contract
administration.
·
More intense negotiations for
additional work because of timeliness is critical
|
Table 1: Comparison between incentive contracts approaches
4.
Selection Criteria
In order to determine which approach
of incentive contract is most appropriate, there are some criteria must be
considered:
Criteria
|
Description
|
Cost uncertainty
|
It is considered appropriate when it is difficult to
estimate the final project cost and the client wishes to avoid the risk of
cost escalation.
|
Uncertainty of scope
|
It
is appropriate when the technical characteristics of the project are not
specifically defined.
|
Process uncertainty
|
It is useful in situation where project methodologies are
unknow at start or are expected to be complex.
|
Value for money
|
It
provides the most efficient method for obtaining value of money.
|
Criticality of
schedule
|
It is appropriate when the duration of the contract is
critical.
|
Performance
Criticality
|
It
provides incentive for excellent quality and avoids cutting corners.
|
Availability for
extra resources
|
It requires adequate staff in numbers and experience to
supervise and/or manage the contract.
|
Contracture
difficulties
|
It
is simple to implement and does not require specialized calculations.
|
Claims
|
It reduces the number of claims expected.
|
Table 2: Rating Scale for each Criteria used in the evaluation
5.
Analysis and
comparison of the Alternative
In this blog, I will analyze and compare the alternatives by
using compensatory models. The attributes of the contract type as shown in
table 3 below.
Attribute
|
Cost Plus Incentive
|
Fixed Price Incentive
|
Lane Rental Approach
|
Incentive
and Disincentive
|
Cost-plus-Time
|
Cost uncertainty
|
Easy
|
Difficult
|
Easy
|
Easy
|
Difficult
|
Uncertainty of scope
|
Good
|
Fair
|
Good
|
Poor
|
Poor
|
Process uncertainty
|
Good
|
Fair
|
Good
|
Poor
|
Poor
|
Value for money
|
Poor
|
Fair
|
Poor
|
Good
|
Fair
|
Criticality of schedule
|
Share
|
Minimum
|
Share
|
Maximum
|
Maximum
|
Performance Criticality
|
Harder
|
Easy
|
Harder
|
Easy
|
Harder
|
Availability for extra resources
|
Easy
|
Easy
|
Harder
|
Harder
|
Easy
|
Contracture difficulties
|
Fair
|
Good
|
Fair
|
Good
|
Poor
|
Claims
|
Easy
|
Harder
|
Easy
|
Harder
|
Easy
|
Table 3: Attribute of Incentive Contract Approach
The
data in the table above are driven from advantage and disadvantage matrix.
Next
step is to rank the attribute using non-dimensional
scaling. Table 4 below shows the ranking clearly.
Attribute
|
Value
|
Relative Rank
|
Dimensional value
|
Cost uncertainty
|
Difficult
|
1
|
0.00
|
Easy
|
2
|
1.00
|
|
Uncertainty of scope
|
Good
|
3
|
1.00
|
Fair
|
2
|
0.50
|
|
Poor
|
1
|
0.00
|
|
Process uncertainty
|
Good
|
3
|
1.00
|
Fair
|
2
|
0.50
|
|
Poor
|
1
|
0.00
|
|
Value for money
|
Good
|
3
|
1.00
|
Fair
|
2
|
0.50
|
|
Poor
|
1
|
0.00
|
|
Criticality of schedule
|
Minimum
|
3
|
1.00
|
Share
|
2
|
0.50
|
|
Maximum
|
1
|
0.00
|
|
Performance Criticality
|
Harder
|
1
|
0.00
|
Easy
|
2
|
1.00
|
|
Availability for extra resources
|
Harder
|
1
|
0.00
|
Easy
|
2
|
1.00
|
|
Contracture difficulties
|
Good
|
3
|
1.00
|
Fair
|
2
|
0.50
|
|
Poor
|
1
|
0.00
|
|
Claims
|
Harder
|
1
|
0.00
|
Easy
|
2
|
1.00
|
Table 4: Non-Dimensional Scaling
After
setting relative rank for each attribute, further is to conduct additive
weighting for all alternatives as shown in table 5.
Attribute
|
Relative
Rank
|
Normalized
Weight (a)
|
Cost Plus Incentive
|
Fixed Price Incentive
|
Lane Rental Approach
|
Incentive
and Disincentive
|
Cost-plus-Time
|
|||||
b
|
a*b
|
b
|
a*b
|
b
|
a*b
|
b
|
a*b
|
b
|
a*b
|
|||
Cost uncertainty
|
9
|
0.20
|
2
|
0.4
|
1
|
0.2
|
2
|
0.4
|
2
|
0.4
|
1
|
0.2
|
Uncertainty of scope
|
8
|
0.18
|
3
|
0.54
|
2
|
0.36
|
3
|
0.54
|
1
|
0.18
|
1
|
0.18
|
Process uncertainty
|
7
|
0.16
|
3
|
0.48
|
2
|
0.32
|
3
|
0.48
|
1
|
0.16
|
1
|
0.16
|
Value for money
|
6
|
0.13
|
1
|
0.13
|
2
|
0.26
|
1
|
0.13
|
3
|
0.39
|
2
|
0.26
|
Criticality of schedule
|
5
|
0.11
|
2
|
0.22
|
3
|
0.33
|
2
|
0.22
|
1
|
0.11
|
1
|
0.11
|
Performance Criticality
|
4
|
0.09
|
1
|
0.09
|
2
|
0.18
|
1
|
0.09
|
2
|
0.18
|
1
|
0.09
|
Availability for extra resources
|
3
|
0.07
|
2
|
0.14
|
2
|
0.14
|
1
|
0.07
|
1
|
0.07
|
2
|
0.14
|
Contracture difficulties
|
2
|
0.04
|
2
|
0.08
|
3
|
0.12
|
2
|
0.08
|
3
|
0.12
|
1
|
0.04
|
Claims
|
1
|
0.02
|
2
|
0.04
|
1
|
0.02
|
2
|
0.04
|
1
|
0.02
|
2
|
0.04
|
1.00
|
2.12
|
1.93
|
2.05
|
1.63
|
1.22
|
Table 5: Weighting for Alternatives
6. Selection of the preferred Alternative
Base from above calculation Cost Plus Incentive become the best alternatives to replace FFP contract type for
our project.
7. Performance Monitoring and the Post Evaluation of
result
Management should consider using incentive contract
type with cost plus incentive approach as the best alternatives to replace FFP
contract type to avoid over budget project and monitoring should be conducted
during the project contract to ensure that all requirements are met.
The result may be incorrect in this case study because
my lack experience in the incentive contract approaches, this blog will be
revised after I gain a lot of experience in this field so I can give accurate
scores for each approach.
References:
1.
US Legal, I.
(2018). Incentive Contract Law and Legal Definition | USLegal, Inc.. Definitions.uslegal.com.
Retrieved 7 January 2018, from https://definitions.uslegal.com/i/incentive-contract/
2.
W10_Afra_Contract
Type for Project. (2018). Pmpopwp.blogspot.com. Retrieved 7 January 2018, from http://pmpopwp.blogspot.com/2018/01/w10afracontract-type-for-project.html#comments
3.
9.5 Selecting
the Type of Contract | Project Management for Instructional Designers. (2018).
Pm4id.org. Retrieved 8 January 2018, from https://pm4id.org/chapter/9-5-selecting-the-type-of-contract/
4.
dvantages &
Disadvantages of a Fixed-Price Contract. (2018). Smallbusiness.chron.com.
Retrieved 8 January 2018, from http://smallbusiness.chron.com/advantages-disadvantages-fixedprice-contract-21066.html
5.
ntoniou, F.,
Aretoulis, G., Konstantinidis, D., & Kalfakakou, G. (2018). Selection
Criteria Used for the Choice of Contract Type for Major Highway Construction
Projects. Retrieved 8 January 2018, from https://ac.els-cdn.com/S1877042812030571/1-s2.0-S1877042812030571-main.pdf?_tid=e5ae2cfa-f448-11e7-b13b-00000aab0f27&acdnat=1515398148_4761b1e466226b0f0118df5723a2a59d
WOW!!! Another OUTSTANDING blog posting, Afra!!!
ReplyDeleteGiven that your top ranked result was "cost plus incentive" contracting, you may find AIA's Integrated Project Delivery Guide to be of further interest to you?
https://www.aiacontracts.org/resources/64146-integrated-project-delivery-a-guide
In this model, cost plus incentive contracts are the norm with the bonuses given/earned by meeting owner's objectives. The very essence of "Doggy Biscuit Project Management".
Keep up the really good work!!
BR,
Dr. PDG, Jakarta