W8__Hamda__ Determining the amount of Incentives and
Disincentives for Power and Water Projects__Part2
1-
Problem
Definition
Any project in the world example Industrial Projects
such as: Power Generation plants, Water Desalination plants, Power and Water
Plants, Refineries, and any other industrial projects have 3 main stages. The
first stage is the Bidding stage, where all the project details, and all
specifications refer to the design of the plant and the technologies to be
used, the site selected for the project are set in such documents- Project
Definition Documents. The second stage which is the main important stage in the
project life cycle since the third stage depends on it is the Implementation
stage or in other word is the Construction stage. In this stage, the
construction of the project will be started, so any fault or any delay in this
stage will cause a delay in the whole project which will cause a delay in the
production of the project which will put the different parties of the projects
in troubles. So, to avoid the construction delays or other difficulties during
the Construction Stage, the proper planning and scheduling of the project tasks
and activities will be very useful. Moreover, there is another way that can be
implemented to avoid any delays in the construction side, which can be
implemented contractually in the Contract. This way is to applied Incentive Contracts
or it can be Incentive Clause in the such Agreements. This blog and the coming
blogs will discuss the way of determining the amount of incentives and
disincentives.
2-
Identify
the Feasible Alternative
FHWA’s Contract Administration Core
Curriculum (CACC) Manual defines I/D for early completion as “A contract
provision which compensates the contractor for each day that identified
critical work is completed ahead of schedule and assesses a deduction for each
day that completion of the critical work is delayed.
In order to establish the amount of Incentives to be paid from the
Owner Company to the Contractor and when to be paid, important to have a
specific curve known as Total Cumulative Project Cost (Owner and
Contractor) which is a combination of
·
Total
Contractor’s Cost Curve
·
Total
Cumulative Owner Overhead and Lost Opportunity Cost.
These
curves will be determined separately, each one in each blog.
3-
Development
of the outcome of Alternative
In this blog, a project with 500 MW will be
studied and analyzed. This project will take 30 months to be duly completed. The
Cost Estimate for this project (the cumulative cost of contractor and owner) is
($2.85 Billion). As shown in table 1.
Contractor Estimates
|
US $ Billion
|
Engineering
|
0.250
|
Procurement
|
0.900
|
Construction
|
0.750
|
Total
|
1.90
|
Owner’s Costs
|
US $ Billion
|
PMT & Support
|
0.650
|
Office Cost
|
0.150
|
Others
|
0.150
|
Total
|
0.950
|
Overall Total
|
2.85
|
The next alternative to be developed in this
blog (part 2) is The Total
Cumulative Owner Overhead and Lost Opportunity Cost. The
total cumulative owner and lost opportunity cost curve consist of different
costs such as the owner’s PMT costs and the Offices costs from month 1 and
onwards, and along with the Lost Opportunity costs from month 25 and onwards.
The below two figures show the build-up of values.
4-
Selection Criteria
5-
Analysis and
comparison of the Alternative
Figure 3 shows the curve of the Owner’s overhead and opportunity
costs by using the data in the above tables. As seen from the figure, the
opportunity cost appears in the month 27 and onwards and it is increase
from one month to another.
6-
Selection of the preferred Alternative
No alternative for this curve, and as it’s part of a three-blog
posting which ends with the development of the Total Cumulative Project Costs.
7-
Performance Monitoring and the Post Evaluation of result
As this blog is part of a series number of blogs, until last
blog (3rd or 4th) is complete, the post-evaluation
performance cannot be performed until the full model is completed.
References:
1-
Stephen J.C. Paterson (2017), Incentivizing Early Completion of
Major Oil and Gas Projects, from http://pmworldjournal.net/wp-content/uploads/2017/11/pmwj64-Nov2017-Paterson-incentivizing-early-completion-of-oil-and-gas-projects.pdf
2- Hamda Al Malki (2017), Incentive
Contracts and its effects on Power and Water projects, Retrieved on 8 January 2018.
3- Afra Al-alawi (2017), Cost and Time Trade-Off,
from http://pmpopwp.blogspot.com/2017/12/w5afracost-and-time-trade-off-part-2.html
Still looking VERY good!!!! You seem to have grasped this concept very well and I honestly hope it will help you grow in your career as not everyone understands this concept fully yet, even though it is very obvious in our day to day personal lives. (It takes 9 months for a women to produce a healthy baby.......!!)
ReplyDeleteLet's see what your conclusion shows us....
BR,
Dr. PDG, Jakarta