W7.1__Hamda__ Determining the amount of Incentives and
Disincentives for Power and Water Projects__Part1
1-
Problem
Definition
Any project in the world example Industrial Projects
such as: Power Generation plants, Water Desalination plants, Power and Water
Plants, Refineries, and any other industrial projects have 3 main stages. The
first stage is the Bidding stage, where all the project details, and all
specifications refer to the design of the plant and the technologies to be
used, the site selected for the project are set in such documents- Project
Definition Documents. The second stage which is the main important stage in the
project life cycle since the third stage depends on it is the Implementation
stage or in other word is the Construction stage. In this stage, the
construction of the project will be started, so any fault or any delay in this
stage will cause a delay in the whole project which will cause a delay in the
production of the project which will put the different parties of the projects
in troubles. So, to avoid the construction delays or other difficulties during
the Construction Stage, the proper planning and scheduling of the project tasks
and activities will be very useful. Moreover, there is another way that can be
implemented to avoid any delays in the construction side, which can be
implemented contractually in the Contract. This way is to applied Incentive Contracts
or it can be Incentive Clause in the such Agreements. This blog and the coming
blogs will discuss the way of determining the amount of incentives and
disincentives.
2-
Identify
the Feasible Alternative
FHWA’s Contract Administration Core
Curriculum (CACC) Manual defines I/D for early completion as “A contract
provision which compensates the contractor for each day that identified
critical work is completed ahead of schedule and assesses a deduction for each
day that completion of the critical work is delayed.
In order to establish the amount of Incentives to be paid from the
Owner Company to the Contractor and when to be paid, important to have a
specific curve known as Total Cumulative Project Cost (Owner and
Contractor) which is a combination of
·
Total
Contractor’s Cost Curve
·
Total
Cumulative Owner Overhead and Lost Opportunity Cost.
These
curves will be determined separately, each one in each blog.
3-
Development
of the outcome of Alternative
In this blog, a project with 500 MW will be
studied and analyzed. This project will take 30 months to be duly completed. The
Cost Estimate for this project (the cumulative cost of contractor and owner) is
($2.85 Billion). As shown in table 1.
Contractor Estimates
|
US $ Billion
|
Engineering
|
0.250
|
Procurement
|
0.900
|
Construction
|
0.750
|
Total
|
1.90
|
Owner’s Costs
|
US $ Billion
|
PMT & Support
|
0.650
|
Office Cost
|
0.150
|
Others
|
0.150
|
Total
|
0.950
|
Overall Total
|
2.85
|
The first alternative to be developed in this
blog is The Total Contractor’s Cost Curve. It can be determined by using
Learning Curve method. And for this above project, different learning curve
ratios are selected and at the end of this blog. One learning curve will be
selected. By using this method, the
contractor curve will consist of 3 main points. The right- hand side point
represents the delay costs and consists only of the contractors extended
overhead costs. However, the left-hand side point represents the accelerate
costs. The mid-point should be the Contractor’s optimum duration. And as shown
in table 1 and the description of Learning Rate curve, the specified project
which is an exponential decay curve that reaches a point at 30-month
which is $1.90B, then climbs upwards with the contractor delay costs due
to the contractor’s delay in submitting the project. Different learning curves
will be developed with different efficiency factor and learning curve ratio,
and the suitable one for this project will be selected considering that the acceleration
of the project is from month 1 to month 30 (month of completing the project)
and the delay of the project is starting after month 30.
4- Selection Criteria
Figure 1: Comparison of Evaluating
Learning Curve
5-
Analysis and comparison of the Alternative
6-
Selection of the preferred Alternative
According to concept of that the suitable learning curve to
be selected is that the higher
the learning curve the lower the inefficiency/the acceleration cost and via
versa, and as shown in above figure, the best curve to fit the model is the 91% EF / 9% LCR
which is the closest Curve to month-24 which is the owner’s Target.
7-
Performance Monitoring and the Post Evaluation of result
As this blog is part of a series number of blogs, until last
blog (3rd or 4th) is complete, the post-evaluation
performance cannot be performed until the full model is completed.
References:
1-
Stephen J.C. Paterson (2017), Incentivizing Early Completion of
Major Oil and Gas Projects, from http://pmworldjournal.net/wp-content/uploads/2017/11/pmwj64-Nov2017-Paterson-incentivizing-early-completion-of-oil-and-gas-projects.pdf
2- Hamda Al Malki (2017), Incentive
Contracts and its effects on Power and Water projects, Retrieved on 8 January 2018.
3-
Incentive Contracting - Incentives, Award
Fee, Award Term, from https://www.dau.mil/acquipedia/Pages/ArticleDetails.aspx?aid=1c0fe484-43f8-4149-97bf-63bafefdf8ae
EXCELLENT Hamda..... Now you've got it.......
ReplyDeleteLet's see where you take us with it....
BR,
Dr. PDG, Jakarta