Opportunity Statement
Currently, the spot market team has only three employees.
As the project progress, the team is expected to gradually grow as more
responsibilities fall on it. The team is currently located at the same office
as all the other teams of OPWP, which is the fifth floor of Muscat Grand Mall.
However, the size of the office is limited and will reach its full capacity
soon. Therefore, it is critical to plan for where to locate the team as it
keeps growing.
In this post, we will compare between different options of where to locate the spot market team and the company as a whole.
In this post, we will compare between different options of where to locate the spot market team and the company as a whole.
Feasible Alternatives
Three alternatives on how to deal with the growth of the
company and where to locate the spot market team and other OPWP teams are
examined:
Option 1) Relocate the spot market team to
another floor of the mall, while keeping the other teams at the fifth floor.
Option 2) Relocate the spot market team to an office outside the mall,
while keeping the other teams at the Mall.
Option 3) Relocate the whole company to a bigger office somewhere else,
keeping all teams together.
Outcomes of Feasible Alternatives
The alternatives will be compared using the compensatory
model of the Multi-Attribute Decision Making Technique. The compensatory model
includes two techniques; the Non-Dimensional Scaling Technique, and the
Additive Weighting Technique. In this model, the relative importance of the
attributes is taken into consideration by giving each of them a weight. The
naming of the compensatory model comes from the fact that a weakness in an
attribute of a product can be compensated by the strength of that product in
another attribute in the model.
Acceptable Criteria
Three criteria will be used to compare between the alternatives:
1)
Cost of relocation: the cost of relocating employees and equipment to a new
office. Also includes other costs such as costs on employees for potentially
relocating their families in case of a new office.
2)
Communication: how easy it is to communicate between members of the
company. Communication affects team building, team spirit, knowledge sharing,
trust between members, collaboration, and also the time projects take to get
done.
3)
Rental Cost: How expensive it is to rent the office space for the
entire staff.
4)
Convenience: How convenient the overall process is of expanding the
office space occupied by the staff, including the process of moving equipment
and documents.
Analysis and Comparison of
the Alternatives
Table 1 below details the value of all attributes for
each of the alternatives.
Table 1:
Data Summary
Attribute
|
Option
1
|
Option
2
|
Option
3
|
Cost
of relocation ($)*
|
10
|
30
|
110
|
Communication
|
medium
|
low
|
high
|
Rental
Cost ($) *
|
90
|
75
|
65
|
Convenience
|
high
|
medium
|
low
|
* Those number are
multiplied by a factor.
We apply the first technique in the model, which is the
non-dimensional scaling technique. In order to do so, the attributes must be
converted and measured in a common measurement scale, which in our case is a
dimensionless unit with a base of 1. The following two equations can be used,
depending on whether the attribute is desirable or undesirable:
·
Desirable:
·
Undesirable:
The results of the technique are summarized in table 2
below:
Table 2:
Non-Dimensional Scaling Technique Results
Attribute
|
Value
|
Formula
|
Dimensionless Value
|
Cost of relocation ($)
(undesirable)
|
10
|
=(110-10)/(110-10)
|
1.00
|
30
|
=(110-30)/(110-10)
|
0.80
|
|
110
|
=(110-110)/(110-10)
|
0.00
|
|
Communication (Relative Rank)
(desirable)
|
medium (2)
|
Relative Rank (2-1)/(3-1)
|
0.50
|
low (1)
|
Relative Rank (1-1)/(3-1)
|
0.00
|
|
high (3)
|
Relative Rank (3-1)/(3-1)
|
1.00
|
|
Rental Cost ($)
(undesirable)
|
90
|
=(90-90)/(90-65)
|
0.00
|
75
|
=(90-75)/(90-65)
|
0.60
|
|
65
|
=(90-65)/(90-65)
|
1.00
|
|
Convenience (Relative Rank)
(desirable)
|
high (3)
|
Relative Rank (3-1)/(3-1)
|
1.00
|
medium (2)
|
Relative Rank (2-1)/(3-1)
|
0.50
|
|
low (1)
|
Relative Rank (1-1)/(3-1)
|
0.00
|
Because of the common scale, the value of all attributes related to each option can be added and then compared, which is shown in table 3 below.
Table 3:
Non-Dimensional Scaling Technique Summary
Attribute
|
Option 1
|
Option 2
|
Option 3
|
Cost of relocation ($)
|
1.00
|
0.80
|
0.00
|
Communication
|
0.50
|
0.00
|
1.00
|
Rental Cost ($)
|
0.00
|
0.60
|
1.00
|
Convenience
|
1.00
|
0.50
|
0.00
|
Total
|
2.50
|
1.90
|
2.00
|
According to this technique, option 1 is the most
favorable. The non-dimensional technique, however, considers that all
attributes are weighted equally, which is not necessarily true. In our case, we
value communication more than we value cost of relocation which we, in turn,
value more than convenience. To take into account, this technique is
complemented by the Additive Weighting Technique. This technique gives more
weight to the attributes that are of higher value to the person performing the
comparison. The results of this technique is summarized in table 4 below. Note
that “B” in the table is the relevant dimensionless value from table 3 above.
Table 4:
Additive Weighting Technique Results
Attribute
|
Relative Rank
|
Normalized Weight (A)
|
Option 1
|
Option 2
|
Option 3
|
||||
|
|
Equation
|
A
|
B
|
A*B
|
B
|
A*B
|
B
|
A*B
|
Convenience
|
1
|
=Relative Rank / ∑Relative Ranks
|
0.100
|
1.000
|
0.100
|
0.500
|
0.050
|
0.000
|
0.000
|
Cost of relocation ($)
|
2
|
0.200
|
1.000
|
0.200
|
0.800
|
0.160
|
0.000
|
0.000
|
|
Rental Cost ($)
|
3
|
0.300
|
0.000
|
0.000
|
0.600
|
0.180
|
1.000
|
0.300
|
|
Communication
|
4
|
0.400
|
0.500
|
0.200
|
0.000
|
0.000
|
1.000
|
0.400
|
|
Total
|
10
|
-
|
1.000
|
-
|
0.500
|
-
|
0.390
|
-
|
0.700
|
As per this technique, option 3 is the most favorable.
Preferred Alternative
According the first technique, option 1 is the most
favorable. However, OPWP values communication more than we value cost of relocation
and rent. The Additive Weighting Technique allowed me to give more weight to
the attributes I value more. Using the second technique which builds upon the
results of the non-dimensional scaling technique, it turns out that my true
preferred option is option 3. Although moving the whole team outside the mall
to a new office is inconvenient and will be costly in terms of relocation, it
is more preferable because of the benefits of strong communication between the
team. Additionally, offices outside the mall are available for better prices
than the mall.
Tracking and Reporting
We shall track the growth of the spot market team and
OPWP overall and compare the size of the team to the available space on a consistent
basis. Once the office space is about to reach its full capacity, we shall look
around for office space options. We will consider the rental cost of the office
space in the mall, and look for options outside the mall. Then, we can run the
same analysis again before making the choice of moving the team.
References
1)
GUILD
OF PROJECT CONTROLS COMPENDIUM and REFERENCE (CaR) | Project Controls -
planning, scheduling, cost management and forensic analysis (Planning Planet).
(n.d.). Retrieved from
http://www.planningplanet.com/guild/gpccar/managing-change-the-owners-perspective
2)
Decision Models: Compensatory and Noncompensatory. (n.d.).
Retrieved from http://www.mycbbook.com/MYCBBook-Consumer-Decision-Judgment-Models.pdf
3)
Decision
Making Considering Multiattributes.
(2012). Retrieved from
http://www.csun.edu/~ghe59995/MSE604/MSE604%20Ch.%2014%20-%20Decision%20Making%20Considering%20Multi-attributes.ppt
4)
W3_YN_Compensatory
Model in MADM. (2017, November 21). Retrieved from
http://pmpopwp.blogspot.com/2017/11/w3yncompensatory-model-in-madm.html
PERFECT Yaarub!!! Doesn't get any better than this...... You are using not only one but two tools that you learned in this course......
ReplyDeleteTHAT is how we generate a return on training investment!!!!
Now I really need you to focus on experimenting with other tools/techniques from PMBOK in your day to day working environment as I need to help you prepare to pass your esam in the coming weeks.
BR,
Dr. PDG, Jakarta