w4_Estimation of Water Projects Duration Using PERT_Thuraiya
Estimation of Water Projects Duration Using PERT 1- Problem identification: Water Projects must meet the Scheduled Commencement Operational Day as it planned to be on operation to meet the demand at that day. However, many projects are delivered later that what is scheduled. This blog studies the most suitable duration for constructing water project. 2- Feasible Alternatives Currently we allow the developer to construct the project in 33 months so the feasible alternatives are: 1- To keep the period of 33 months. 2- To agree on the result of Pert analysis that will be shown in this blog. 3- Development of the outcome of the alternatives PERT (Program Evaluation and Review Technique) is one of the successful and proven methods among the many other techniques. Using Pert Technique and based on Historical Da...