W4_Afra_Cost and Time Trade-Off Part 1
1. Problem
Recognition
There is a
relationship between project’s completion time and its cost. By understanding
the time-cost relationship, one is better able to predict the impact of a
schedule change on project cost.
The purpose of
this blog is to validate the cost & time trade-offs by using Module 08-7 in
The GUILD which provides a great illustration that is based on the US
Department of Transportation. This validation will be used on my paper to
demonstrate that what was done can work in electricity and water sector.
Figure 1 - Schedule vs Time Optimization
From the figure, the owner's optimum
duration and owner’s optimum is almost always different from the contractor. The
question here is how to define this difference? By finding the difference
between owner’s optimum cost (8) and contractors optimum duration (4) which intersect
with Total cost curve this is what determines the incentives
(I) from the owner to the contractor to complete the project in the
owner’s optimum time frame.
Again, if we have a look at the
difference between contractor optimum cost (10) between where contractors
optimum cost (7) and the P75 duration intersect the contractor cost curve it
provides us with disincentive (D).
The main purpose of this blog is to
determine the best fit for contractor curve (the green line in above figure).
2. Feasible alternatives
The learning curve is the suitable
way to go with. Moreover, different organizations and different products have different
learning curves. The rate of learning curve differs depending on the quality of
management and the potential of the process and product. The lower the number (say
60% compared to 80%) the steeper the slope and the faster
the drop-in costs. For this blog, three options were chosen (different rate)
and these are:
·
85%
Efficiency Factor (EF) / 35% Learning Curve Rate (LCR)
·
90%
Efficiency Factor / 15% Learning Curve Rate
·
95%
Efficiency Factor / 2% Learning Curve Rate
The Efficiency Factor or Company Efficiency Factor is the
company’s degree of success in using the least possible inputs to produce
highest possible output.
The formula for the learning curve is shown in figure 2
below:
Figure 2 – Learning curve formula
Below table shows some of the values for b according to each
learning curve rate:
Learning Rate (%)
|
b
|
80%
|
0.322
|
85%
|
0.234
|
90%
|
0.152
|
95%
|
0.074
|
Table 1 – Learning curve values of b
3. Development of the
outcome of Alternative
The Learning curve will be
determined according to above percentage for learning ratio by using excel
sheet. The learning curve formula will be calculated for each month of the
project (assume 25 months)
The first Model developed was for
the 85% EF / 35% LCR and the curve is shown below.
Figure 3 –
85% Efficiency Factor / 35% Learning
Curve Rate
The second Model developed was for
the 90% EF / 15% LCR and the curve is shown below.
Figure 4 –
90% Efficiency Factor / 15% Learning
Curve Rate
The third Model developed was for
the 95% EF / 2% LCR and the curve is shown below.
Figure 4 – 95% Efficiency Factor / 2% Learning Curve Rate
4.
Selection Criteria
The
power project in OPWP designed to deliver around 1500 MW per day, using either
gas turbine with a specific requirement or steam turbine and a lot of other
equipment. The cost estimation here excludes any bad material used. Each
project facility is based on an Engineering, Procurement and Construction (EPC)
philosophy for design, procure and construct of each portion.
A cost of $1.5 Billion at
month 12 will be used as criteria selection for all three models, and for the
delay costs $0.30 Billion will be used for each month thereafter. As previously
mentioned all three alternatives will use the same delay profile.
5. Analysis
and comparison of the Alternative
Using
previous criteria each model was developed to have a cost of $1.5 Billion at
the month 12 point, and thereafter the delay costs were added monthly.
Figure 5 – 85/35 Accelerated Costs & Delay Cost Chart
Figure 6 – 90/15 Accelerated Costs & Delay Cost Chart
Figure 7 – 95/2 Accelerated Costs & Delay Cost Chart
6.
Selection of the
preferred Alternative
The
following matrix shows the best alternative using the Multi-attribute decision making:
Note:
5 means excellent, 4 good, 3 average, 1 poor.
Attributes
|
85/35
|
90/15
|
95/2
|
Left side (Acceleration)
|
5
|
5
|
3
|
Right side (delay)
|
5
|
5
|
5
|
Data point suitable for acceleration
|
4
|
4
|
1
|
Data point suitable for delay
|
3
|
4
|
1
|
Total
|
17
|
18
|
11
|
Rank
|
2
|
1
|
3
|
Table 2 –
Decision Matrix of Feasible Alternatives
According
to the table, preferred alternative is to use the 90%EF/15% LCR curve
7.
Performance Monitoring
and the Post Evaluation of result
As this blog is part of a series number of blogs,
until last blog (3rd or 4th) is complete, the
post-evaluation performance cannot be performed until the full model is
completed.
References:
1.
Mallela, J.,
& Sadasivam, S. (2011). Figure 15 –Work zone road user costs:
Concepts and applications : final report. U.S. Department of
Transportation, Federal Highway Administration Office of Operations (HOP).
2. Bhatti, A. T.
(2012, November 23).Learning curve phenonemon [Learning curve formula].
Retrieved from https://images.search.yahoo.com/search/images?p=learning+curve+formula&fr=yset_st_sf_ab&imgurl=http%3A%2F%2Fimage.slidesharecdn.com%2Flearningcurve-121123105005-phpapp02%2F95%2Flearning-curve-7-638.jpg%3Fcb%3D1360231937#id=2&iurl=http%3A%2F%2Fimage.slidesharecdn.com%2Flearningcurve-121123105005-phpapp02%2F95%2Flearning-curve-7-638.jpg%3Fcb%3D1360231937&action=click
3.
Time-Cost. (2017).
Netmba.com. Retrieved 27 November 2017, from http://www.netmba.com/operations/project/time-cost/
4.
GUILD OF PROJECT CONTROLS COMPENDIUM
and REFERENCE (CaR) | Project Controls - planning, scheduling, cost management
and forensic analysis (Planning Planet). (2017). Planningplanet.com.
Retrieved 27 November 2017, from http://www.planningplanet.com/guild/gpccar/validate-the-time-and-cost-trade-offs
5. W18_SJP_Cost & Time Trade-off Part 1 -
Achieving Guild of Project Controls / AACE Certification BLOG. (2017). Achieving Guild of Project Controls / AACE Certification BLOG.
Retrieved 27 November 2017, from https://js-pag-cert-2017.com/w18_sjp_cost-time-trade-off-part-1/
AWESOME, Afra!!! Now that you have the CONTRACTORS curve you need to look at YOUR curve..... Going to be very interesting to see what OPWP's curve will look like as you are actually selling the electricity/water that the operating facility produces..
ReplyDeleteLooking forward to seeing that curve...
BR,
Dr. PDG, Jakarta