W3_Muslem_Tendering Options and Cost Estimate for Utilising Extranet Service for OPWP Procurements
Problem Statement:
Extranet is an important element
in OPWP procurement for the purpose of sharing tender documents and information
with suppliers. Currently, OPWP does not utilize extranet, but relies on
contracted advisors to provide this service. In some cases, advisors charge a
cost for it as shown in the table below.
Project
|
Year
|
Cost of Extranet
Service (OMR)*
|
Project A
|
2012
|
4,000.00
|
Project B
|
2013
|
0.00
|
Project C
|
2013
|
0.00
|
Project D
|
2015
|
0.00
|
Project E
|
2016
|
0.00
|
Project F
|
2017
|
20,000.00
|
Project G
|
2017
|
0.00
|
Project H
|
2017
|
0.00
|
*Indicative figures
for the purpose of this report.
Studying historical data and
current situation show that extranet service has been provided free of charge
for most of our projects. However, the high cost of extranet service for
Project F commands a need to study feasible options to procure the service for
OPWP future projects, and provide a good estimate of cost for budget planning.
Feasible Tendering Options:
Normally, there are three modes of
tendering; Open Tenders, Limited Tenders, and Single Tender [1]. OPWP’s
obligations do not allow to adopt Single Tender Mode. Therefore, the two
feasible options for this procurement are Limited (restricted) Tender or Open Tender.
Outcomes and Cost Estimates of Options:
Open tender is the most common
tendering process [2], allowing greater competition, hence better chance to
have competitive bids. Limited tender might produce similar outputs to open
tender for this service as potential tenderers are most likely to be local, and
hence similar service cost. The added advantage of limited tender is the
slightly shorter tendering period.
The extranet cost can be divided
into two sub-costs; portal development cost and hosting cost. As per our IT
Department, the cost for hosting 5GB of data is approximately 1,000 per
year. Our largest project has required 2.6
GB storage for data. The maximum number of large scale projects procured in one
year in PD Department is 6 projects. Therefore, 15GB is required, meaning the
annual cost of hosting is approximately OMR 3,000.
The following table shows cost of the
basic portal development by a number of suppliers.
Suppliers
|
Cost (OMR)
|
Supplier A
|
4,000
|
Supplier B
|
1,925
|
Supplier C
|
5,000
|
Supplier D
|
2,175
|
Supplier E
|
3,000
|
Supplier F
|
2,400
|
Average
|
3,080
|
Three-point (PERT) estimation is
most common estimation technique [3]. The PERT estimate formula is Ce = (Co+4Cm+Cp)/6,
where;
Most
likely Cost (Cm): Average cost of OMR 3,080 is considered in
this case for Cm.
Pessimistic
Cost (Cp): The worst case is OMR 5,000.
Optimistic
Cost (Co): The best case is OMR 1,925.
Therefore, the expected portal development
cost is approximately OMR 3,200.
The following table shows cost
estimates for both options in OMR, assuming that both would offer a similar
cost.
Items
|
Estimated
Cost (OMR)
|
Portal
Development
|
3,200
|
Annual
Hosting Cost
|
3,000
|
Contingency
(10%)
|
620
|
Total
|
6,820*
|
*OMR 3,000 to be paid
on an annual basis.
Selection of Criteria:
Perhaps the most important
criterion is having a competitive bid due to the economic purchase obligation
that OPWP has to adhere to. Another criterion is the procurement timeline due
to the need to procure the service within three month timeframe which is the
period from advisors appointment to the release of Request for Qualification (RfQ) of a project.
Analysis and Comparison of Options:
World Bank guidelines indicate
that limited tender may be suitable where there is a limited number of
suppliers, or other reasons that might justify moving away from open tender
[4]. Limited tender is less competitive than open tender due to the smaller pool
of competition to provide the service [5]. Although open tendering is favorable,
it could face the risk that the tender advertisement might not reach to all
potential tenderers. However, to deal with this risk and have better
competition, it is recommended to conduct a market screening prior release of
tender, and notify potential tenderers of the advertisement.
In term of tendering timeline,
limited tender offers a shorter tendering process by approximately 10 days
which are the usual period of tender purchase for open tender mode. However,
the set three month timeframe is sufficient for both types to be conducted, even
when considering the 40 day tendering period as set by Tender Law.
Recommendation and Selection of Preferred
Option:
Open tender is the best option for
this procurement. It
is recommended that the procurement for extranet service shall not be triggered
unless advisory bids of future projects indicate a need. This is because extranet
service in most OPWP projects is procured by advisors at zero cost as
highlighted earlier. However, RfP Documents for the service shall be prepared
in advance.
Performance Monitoring:
Extranet portal requires annual maintenance
post implementation. This shall be handled by IT Department, along with log-in authorization
requirements. The management of extranet portal, including documents update, will
be handled by project managers in PD Department.
References:
[1] Central Vigilance Commission (ND), Tendering stage, PDF.
Retrieved from; http://cvc.nic.in/3%20Tender%20Stage.pdf
[19 November 2017].
[2] PPP Certification (ND), Main Types of PPP Tender
Processes. Retrieved from; https://ppp-certification.com/ppp-certification-guide/2-main-types-ppp-tender-processes
[20 November 2017].
[3] PM Study Circle (ND), 4 Tools to Estimate Costs in the
Project Management. Retrieved from; https://pmstudycircle.com/2012/06/4-tools-to-estimate-costs-in-the-project-management/
[20 November 2017].
[4] World Bank
(2011), Guidelines Procurement of Goods, Works & Non-Consulting Services; Under IBRD Loans & IDA Credits &
Grants by World Bank Borrowers. PDF. Retrived from; http://documents.worldbank.org/curated/en/634571468152711050/pdf/586680BR0procu0IC0dislosed010170110.pdf
[20 November 2017].
[5] Australian National Audit Office (2015), Limited Tender
Procurement. Retrieved from; https://www.anao.gov.au/work/performance-audit/limited-tender-procurement
[20 November 2017].
Sorry Muslem but I don't see any connection between PERT and how that helps you determine that "Open Tender" is the preferred option? I can see PERT being used to calculate the OWNERS ESTIMATE but I just don't see how PERT can help you make the decision as to which tendering option to use....
ReplyDeleteWhy not try using Multi-Attribute Decision Making (MADM) analysis to answer your perfectly valid question? Repost as W3.1 and then you can do another blog for W4 creating the owners estimate using PERT.
BR,
Dr. PDG, Jakarta
PS as there is no apparent causal relationship between cost and tendering method, break them into two separate blog postings.
ReplyDelete