W2_Nasser_ Estimating Time Required
for Processing a Monthly Invoices using 3 Point Time Estimating (PERT)
A part of my 2017 individual KPI in
my department, Client Contracts & Interface Department (CCI), is processing
3 monthly invoices (being A, B & C) contributing 35% in my overall KPI
score. The 3 monthly invoices normally received from Power and Water Plants
during the operation period by the beginning of every month and to be processed
at least within 20 days from the receipt date.
As “My Time is My Cost” I am
going to use a famous concept named “Three-Point Estimate Techniques “ to
find out the estimated/expected time required for Processing an invoice, assuming
that all 3 invoices will take the same duration.
2. Identify the Feasible Alternative
The Three Point Estimate
technique is used to arrive at a better estimate of the time required to
complete a particular activity, work package, and can be rolled up to the
entire project. Further, this technique can be used for Time as well as Cost. The
following 2 methodologies can be used:
- A Simple Mean, or Triangular Estimate
- A Weighted Average, or Beta Distribution
Figure1: BETA vs.
Triangular Distribution
For deriving the estimated duration for the full
process, the following 3 estimated time durations will
be figured out:
o
The most
optimistic (tO): case where everything goes right
o
The most
likely (tM): case given normal problems and opportunities
o
The most
pessimistic (tP): case when everything goes wrong
Step3:
Calculating
Weighted Average (Estimated Mean) for each activity. It is calculated by a
formula:
Step4:
calculating Standard Deviation for each activity. It is calculated by a formula:
3. Development of the Outcome for Alternative
Step1: All main activities included in the process
of A, B & C monthly invoices are listed below:
1.
Outage Confirmation letter
(P+W)
2.
FDM Run
3.
Check Sheet Preparation
4.
ONF Verification (P+W)
5.
Start-Up Verification
6.
Joint Reading Data Inputs
(P+W)
7.
Final Completion &
Finishing
8.
1st Senior Review
9.
2nd Senior Review
10.
Line Manager Review
11.
Director Review &
submit to Finance
Step2: Based on experience & historical
information the (tO, tM & tP) time durations for each activity were
identified.
Using Triangular Estimate → Mean =(P+M+O)/3
Using Beta
Distribution → PERT =(P+4M+O)/6
Using Triangular Estimate → Activity Standard Deviation (σ) = (P-O)/3
Using Beta
Distribution → Activity Standard Deviation (σ) = (P-O)/6
Step5: calculating Variance for each
activity. It is calculated by a formula:
Using Triangular
Estimate → Activity Variance = σ2= ((P-O)/3)
^2
Using Beta
Distribution → Activity Variance = σ2= ((P-O)/3)
^2
Step6: for total monthly invoice process sum
up all activities value got in Step 3,4&5.
4. Selection Criteria:
The estimated time should be:
-
With Lower chance
(probability) for best case and worst case to occur
-
Reasonable
-
Reliable
-
Reflecting risk or uncertainty associated with
schedule
-
Not far from the most likely time duration
3. Analysis and Comparison of the Alternative:
Table1: Monthly
Invoice time estimated using Triangular Estimate
Table2: Monthly
Invoice time estimated using PERT Estimate
5. Analysis and Comparison of the Alternative
The Estimated Time duration required for processing the
invoice, using the 2 methodologies, was found as below:
-
Using Triangular Estimate;
it is 19.16 hours duration
-
Using Beta Distribution; it
is 18.52 hours duration
5.
Selection
of the Preferred Alternative
The
methodology preferred is Beta Distribution. It is a commonly used weighting might be – there is less
chance of the worst case or the best case happening. In good faith, most likely
estimate (M), is what it will take to get the invoice processed.
6.
Performance Monitoring and the Post Evaluation of
Result
This
estimated cost will be embodied in my monthly schedule to be used as a base time
reference for better management of my time. If our Organizational Process Asset
(OPA) for processing the invoice got changed , then a new time estimate analysis
shall be required at that time.
7.
Reference:
1. Perform PERT (Program Evaluation Review Technique) Analysis Manually on
Schedule
2. Use PERT technique for more accurate estimates
3. PERT Estimation Technique
4. PROJECT EVALUATION REVIEW TECHNIQUE, PERT
5. Point Estimate: Triangular Distribution vs Beta Distribution (PERT)
Hi Nasser, bad news..... I am going to REJECT your blog as you made a FATAL ERROR in your calculations. You CANNOT add up the Standard Deviations in a string of activities as you have done. What you have to do is add up the VARIANCES of each activity and then find the square root of the sum of the variances.
ReplyDeleteYou need to RECALCULATE Tables 1 and 2 and then REPOST your corrected results as a W2.1.
For more on this, go here- https://apcentral.collegeboard.org/courses/ap-statistics/classroom-resources/why-variances-add-and-why-it-matters?course=ap-statistics
BR,
Dr. PDG, Jakarta
primocVcons_ko David Mejia Download
ReplyDeletedoughculavas