W3__Hamda__Using PERT technique in Estimating time duration for
processing Monthly Invoice__
1- Problem Recognition
In each company, each project depends on the estimations
of different aspects such as, the estimating of time will be taken to complete
each activity under the project and the estimating of the costs that will be
incurred in executing any activity or phase under the project. under CCI
department in our company there are several small projects which have START
& FINISH date. One of these main projects is Processing the Monthly Invoices
of different Power and Desalination plants as I discussed in W2 blog. Processing
the Monthly Invoice has a specific FINISH date which is according to the
receipt date of these such invoice. Processing the Monthly Invoice depends on
different things which may affect on completing the task in the specific
scheduled date. In this blog, I will use the Project Evaluation and Review Technique
(PERT) in analyzing this activity and to find the estimated and preferred time
to complete it.
2- Feasible alternative
PERT is a three-point activity estimating technique that considers
estimation uncertainty and risk by using three estimates to define an
approximate probability for an activity’s cost or duration. At activity
level PERT can help us to determine a more realistic estimate. Bell curve, also called a
Normal Distribution curve is one methodology used in PERT technique. Figure
1 shows the Normal Distribution curve.
In order to use this technique, there are 3 main estimated point shall be
known and used which they are:
-
Most likely (Tm) - This is the time duration where
there is a high probability of completing the task within the given time
duration.
-
Optimistic(To) - In this scenario, the estimate is
determined considering all favorable conditions; i.e. it is a best-case
scenario. In other words, you can say that this is the shortest time in which
you may complete the task.
-
Pessimistic(Tp) - Here, estimate is determined
considering all unfavorable conditions; i.e. worst-case scenario. In other
words, this is the longest time the activity might require to complete itself.
The
formula used in calculating the PERT is:
PERT Estimate = (To + 4Tm +
Tp) / 6 & Standard Deviation = (Tp – To)
/ 6 & Variance
(sigma)= ((Tp – To) / 3) ^2
3-
Development of the
outcome of Alternative
Regarding to the above description of one main task/project under CCI
department, the completion of it depends on different tasks such as:
1-
The submitting and receiving Power and Water Outage
Confirmations.
2-
Availability of the all data required in processing the
invoice.
3-
The preparation, editing, and reviewing the sheet of
calculations.
4-
The process of checking the accuracy of such data
received from the Generation.
5-
The process of the plant model (FDM model).
6-
Finalizing the process of monthly invoice.
7-
Reviewing the invoice by the Senior Engineers and approve
it.
8-
Reviewing the invoice by the Department Manager and
approve it.
9-
Reviewing the invoice by the Department Director and
approve it.
10-
Submitting the invoice to Finance Department (FINISH
Date).
From all these tasks, I think the main important tasks that processing the
Monthly Invoice depends on are the first 4 one (tasks from 3-6), Because
completing these four tasks on time which make the other 4 tasks on time.
4- Selection Criteria
Activity
|
Tm of completing it
|
To of completing it
|
Tp of completing it
|
Estimate Duration “PERT”
|
Standard Deviation
|
Variance
|
Task 3
|
3.5
|
2
|
4
|
3.33
|
0.33
|
0.44
|
Task 4
|
3.5
|
2
|
5
|
3.50
|
0.50
|
1.00
|
Task 5
|
8
|
7
|
10
|
8.17
|
0.50
|
1.00
|
Task 6
|
2
|
1.5
|
3.5
|
2.17
|
0.33
|
0.44
|
Remaining last tasks
|
1.5
|
1
|
2
|
1.50
|
0.17
|
0.11
|
activity
|
Tm of completing it
|
To of completing it
|
Tp of completing it
|
Estimate Duration “PERT”
|
Standard Deviation
|
Variance
|
duration in processing
the monthly invoice
|
18.5
|
13.5
|
24.5
|
18.67
|
1.83
|
13.44
|
5- Analysis and comparison of the
Alternative
Table 1 shows the three-estimated
duration for the main tasks in processing the monthly invoice which I mentioned
above in point 3, because completing these task on time will help us in
completing the remaining task on time. They will not take a lot of time as I
mentioned in table 1. As shown in table 1, task 4 & task 5 have the largest
estimate duration “PERT”, Standard Deviation and finally the sigma of it. So,
for them since they have large variance means not completing them on time, will
might cause a risk on our company in completing the monthly invoice.
From table 2, we can say that:
-
Optimistically we can complete the activity in five (13.5) days. There will
be 11.5 days from the Due Date, which is very good estimating duration in
completing the invoice.
-
Pessimistically we estimate that it can take
us up to Fifteen (24.5) days. There will 0.5 (half) day from the Due Date.
-
Most
likely it will take us only seven (18.5) days. There will be 6.5 days from the
Due Date which a quite good. It can be improved by decreasing the number of
days consumed in processing task 4 for example.
6- Selection of the preferred
Alternative
By suing one of the most useful technique in analyzing
and estimating the time and the cost of each activity, or task under any
project or in general case estimating the project duration or cost which is
PERT technique, it is clear from the above tables that the best case of time
duration in processing the monthly invoice is 13.5 days (by taking in our
account the days consumed in each task especially task 4&5). This duration
is actually the best duration because by completing the invoice in period we
will have enough time for other tasks and also remaining days from the Due Date
which will help other department in processing their work on time.
7- Performance Monitoring and the Post
Evaluation of result
Using the PERT technique in calculating the estimated
duration of completing the project and the cost that will be incurred in
executing any project will might be used in calculating the Contingency
Reserve for that project in order to avoid any risk on the company in case
the monthly will not be submitted before the Due Date to Finance Department and
then to the Generator.
References
1- Fahad Usmani,
(2017). A Short Guide to PERT – Program
Evaluation and Review Technique. Retrieved 20 November 2017, from https://pmstudycircle.com/2013/08/pert-program-evaluation-and-review-technique/
2- Dave Fourie,
(2015). What is
PERT and how can we use it? Retrieved 20
November 2017, from https://www.linkedin.com/pulse/what-pert-how-can-we-use-dave-fourie-pmp-prince2-
3- A
Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE), Fifth Edition.
Retrieved
14 November 2017.
Sorry Hamda but you need to go back and look at some of your colleagues postings? Where did you see or find ANYTHING that tells you that you can ADD the Standard Deviations?
ReplyDeleteBetter go back and talk to Mr. Nasser? http://pmpopwp.blogspot.co.id/2017/11/w2.html
Make sure you fix your error and REPOST as your W3.1 blog.....
Don't forget that lesson learned.... It is a really important one....
BR,
Dr. PDG, Jakarta
Dear Dr.Paul, table 2 doesn't shows the summation of Standard Deviation. what I did in table 2 is that I added the most likely period of doing all tasks and the same for all. and then I calculate the mean, Standard deviation and the variance. Please correct me if this way is wrong way?
DeleteAnd I will repost the blog, but I will replace the number of days consumed in doing each task per month by the number of hours. and the calculation will be done
ReplyDelete